CONSTRUCTION UPDATE-03.09.2018

Tower-5-Structure Works

  • Foundation works completed up to EGL-100%
    • All Footing with pedestal column casting completed & Column casting at Stilt floor
  • Structure Works in upper floors
Floor Columns Roof cast Blockwork Wall plaster Ceiling plaster Water proofing Exter plaster
First floor 100% 100% 95% 95% 100% 20% 90%
Second floor 100% 100% 95% 95% 100% 90%
Third Floor 100% 100% 95% 90% 100% 90%
Fourth floor 100% 100% 95% 90% 100% 90%
Fifth floor 100% 100% 95% 80% 100% 70%
Sixth floor 100% 100% 95% 70% 50%
Seventh floor 100% 100% 95%
Eighth floor 100% 100% 90%
Nineth floor 100% 100%