CONSTRUCTION UPDATE-01.12.2017

Block A - Current Status of site progress

  • 3rd Floor roof slab work in progress.
  • 2nd Floor Block work have commenced.
  • 1st floor Block work nearly 80% of work completed.

Block B - Current status of site progress

  • 3rd Floor Column 95% completed balance work in progress.
  • 1st floor Block work have commenced.