CONSTRUCTION UPDATE-10.10.2018

Block A - Current Status of site progress

  • 4th floor internal plastering work in progress.
  • Terrace Waterproofing work in progress.
  • Apartment internal Plumbing work in progress.
  • External Plastering 75% completed balance work base preparation is in progress.
  • External painting work in progress.
  • Toilet water proofing work in progress.
  • OHT Water proofing work in progress.
  • Grade slab work completed.
  • 1st Floor Tilling work in progress.
  • 1st coat putty work in progress.

Block B - Current status of site progress

  • Internal Plastering completed.
  • Apartment internal Plumbing work in progress.
  • Above terrace Head room and Pergola plastering work in progress.
  • OHT cover slab concrete work in progress.
  • 1st floor tilling work in progress.
  • 1st coat putty work in progress.