CONSTRUCTION UPDATE-01.08.2018

Block A - Current Status of site progress

  • 4th Floor Block work 98% completed.
  • 4th Floor Toilet rough plastering work in progress.
  • Terrace Pergola/Head Room work in progress.
  • Apartment internal electrical work upto 3rd floor is completed and 4th Floor is in progress.
  • Apartment internal Plumbing work upto 2nd Floor completed and other floors are in progress.
  • External Plastering work is in progress.

Block B - Current status of site progress

  • Internal Plaster completed upto to 3rd Floor and 4th Floor work in progress.
  • Apartment internal electrical work completed.
  • Apartment internal Plumbing work upto 2nd Floor completed and other floors are in progress.
  • Waterproofing work is commenced in FF Toilets & Balcony area.
  • Above terrace Head room and Pergola column work in progress.

Common Area Status

  • Block A bio-septic tank work completed.
  • Grade slab base preparation work in progress for A block.