CONSTRUCTION UPDATE-03.11.2018

Block A - Current Status of site progress

  • 4th floor internal plastering work in progress.
  • Terrace Waterproofing work in progress.
  • Apartment internal Plumbing work in progress.
  • External Plastering 95% completed balance work base preparation is in progress.
  • External painting work in progress.
  • Toilet water proofing work in progress.
  • OHT Water proofing work in progress.
  • 2nd Floor Tilling work in progress.
  • 1st Floor 2nd coat putty work in progress.

Block B - Current status of site progress

  • Above terrace Head room and Pergola plastering work in progress.
  • OHT Water proofing work in progress.
  • 2nd floor tilling work in progress.
  • 1st Floor 2nd coat putty work in progress.

Common Area

  • OSR Compound wall work in progress.
  • Strom water drain work in progress.